– in one procurement procedure, an increase of 32 % was observed in comparison to the initial cost estimate; notes furthermore that in two other procurement procedures, due to the nature of the informati
on available in the files, the reconciliation of the difference between
the final contract value with the initial estimation value was proven as complicated; ac
knowledges from the Joint Undertaking that the complexity of the recon
...[+++]ciliation is due to the re-evaluation of the initial scope of the contract, which led to an increase of time as well as to the nature, complexity and amounts involved in such contracts;
– dans une procédure de marché, une augmentation des coûts de 32 % a été constatée par rapport à l'estimation initiale; note en outre que, dans deux autres procédures de marchés, la nature des informations figurant dans les dossiers a rendu complexe l'explication de la différence entre la valeur finale du marché et sa valeur estimée initiale; note que, d'après l'entreprise commune, la complexité de cette explication est due à la réévaluation du champ d'application initial du marché, qui a demandé plus de temps, ainsi qu'à la nature, à la complexité et aux montants concernés par ces marchés;